Technical details
Client
Western Australia State Government
Dates

Completed 2019

Missions
Structural engineering, Civil engineering
Location
Perth, WA, Australia
Activity
Buildings, Education

The first phase established the core of a campus subsequently expanded through Stage 2 to accommodate up to 2,000 students. Stage 1 included a 150-seat lecture theatre, modern library and large multipurpose indoor sports hall.

A podium-based campus structure

Stage 1 comprises four interconnected three-storey buildings arranged around a large landscaped podium suspended over an underground car park and classrooms below. 

The concrete structure uses widely spaced columns and post-tensioned floor slabs, creating spans of up to 11 metres while allowing some spaces to be adapted over time. A 115 by 50 metre post-tensioned landscaped podium slab links two of the buildings and forms a major element of the campus.

Resolving a complex site constraint

A key challenge was the presence of a Water Corporation easement beneath the site. BG&E played a central role in negotiations with the utility, enabling the development of a compliant piled structural solution that allowed the school to be constructed over the easement, a resolution critical to the viability of the design.