This West deck, a metallic structure of 4,750 tonnes, will enable trains along the route to cross towards Curzon Street Station in Birmingham city centre and destinations in the north, including Manchester, Liverpool and Glasgow.
It was installed by hoisting it above the motorway carriageways in both directions using powerful hydraulic jacks. The operation took nine hours, whilst traffic continued to flow below, thereby minimising disruption to motorists.
This milestone marks the completion of the structural works on the M6 South viaducts, the structural design of which was carried out by the Balfour Beatty VINCI consortium, comprising Mott MacDonald and SYSTRA, as well as Weston Williamson + Partners. The East deck, which will carry trains bound for the two London HS2 stations, Old Oak Common and Euston, was installed in 2025.