05 August 2026
The installation of the final roof segment of the Burton Green tunnel on the HS2 network marks a major milestone for the 700-metre-long structure in the West Midlands, designed to integrate the new railway into the surrounding village and landscape.
Major tunnel milestone on the UK’s HS2 network

HS2 engineers have installed the final roof segment on the Burton Green tunnel, near the town of Kenilworth, completing the main structure of one of the five ‘green tunnels’ being built along the route.

The 16-metre-wide, twin-box tunnel will carry high-speed trains beneath the village of Burton Green. An internal wall separates trains travelling in each direction.

With the structure now complete, engineers and ecologists will turn their attention to the tunnel’s 500-metre-long green roof. Trees, plants and shrubs will be planted above the structure to help it blend into the surrounding landscape and create green space for local communities.

A railway within the landscape

Connectivity and access have been central to the project. Once the works are complete, the Kenilworth Greenway will be reinstated close to its original alignment above the tunnel. It will provide a route between Balsall Common and Kenilworth, via Burton Green, for walkers, cyclists and horse riders.

The design also had to address the constraints of constructing the tunnel within a narrow corridor through the village.

The completed scheme will restore the original character of the Kenilworth Greenway and reconnect it with the wider ecological landscape above the buried tunnel.

Material excavated during construction is being reused for the wider landscaping works. The planting of native trees and shrubs will create habitats for wildlife and restore vegetated connections with the nearby Black Waste Wood and Little Poors Wood.

A cut-and-cover green tunnel

Burton Green is being built using the cut-and-cover method. These structures are shallower than conventional deep, twin-bore tunnels and are covered with vegetation to reduce their visual impact and integrate the railway into its surroundings.

Work is continuing on the tunnel’s final elements, including an escape walkway and fire protection for the upper walls. Throughout construction, the programme has been carefully planned to maintain vehicle and pedestrian access through Burton Green.

Don't miss anything, follow us on social media!