10 June 2025
The first part of a 320-metre-long viaduct has been slid into position over the M6, marking another significant milestone on the HS2 project in the Midlands.

Using material similar to that found on non-stick frying pans, the first of three giant sections was moved into place during a 29-hour closure. The ‘East Deck’ section was slid 119 metres out over a slip road adjacent to the motorway, and the road reopened 11 hours ahead of schedule.

A wide angle shot of the M6 South viaduct being moved into position on the HS2 project.
The first section of the M6 South viaduct sliding into position

The viaduct deck is being assembled to one side and slid across the motorway over three weekends, with each part pushed out before later sections are added behind them. This multi-stage process means that the weight of the deck will increase with each push from 1,300 tonnes for the first slide, to 3,290 for the final one, which will take the deck out over the main M6 carriageway and then finally the M6-M42 link roads.

The East Deck will carry two tracks taking trains towards London while an adjacent West Deck will carry a further two tracks for services heading to Birmingham and further north. This will be assembled and slid out next year using the same technique.

A construction worker wearing bright orange PPE is pictured inserting non-stick pads under the deck beam of the M6 South viaduct deck on the HS2 project. The photo is taken through a 'window' of the deck beam. Behind the construction worker are lots of blurred trees.
Non-stick pads being inserted under the deck beam

Each viaduct span is formed of a hollow double-box structure made of weathering steel. This kind of steel boasts a natural protective layer of oxidisation which gives it a characteristic ‘rusty’ appearance and reduces maintenance by eliminating the need for regular repainting. Four pairs of concrete piers support the viaducts with tallest one 9.9m in height. A 4.5m high parapet will be provided on the side facing the Chelmsely Wood to reduce noise and disturbance from passing trains.

The structural design has been carried out by Balfour Beatty VINCI’s Design Joint Venture (DJV), made up of Mott MacDonald and SYSTRA.

Tom Dutton, Senior Design Co-ordinator for the Mott MacDonald SYSTRA DJV, said: “The launch of the first deck of the two-deck M6 Motorway South Viaduct marks an exciting milestone following years of dedicated design work. We have seen the design take shape as the foundations, piers, and abutments were constructed, and now the moment has arrived for the deck to be launched.

View along the side of the M6 South viaduct deck as it's being installed on the HS2 project. A construction worker wearing PPE is pictured on some scaffolding next to the large structure. The construction site is in the background.
View along the side of the M6 South viaduct deck

“The launch design is a fantastic example of collaboration between Mott MacDonald SYSTRA DJV colleagues in the UK and France, BBV, and their steelwork and launching contractor, Victor Buyck Steel Construction. Together, we have addressed the complex challenges of the temporary works and the fabrication of the steel diaphragm—not to mention the feat of launching the viaduct decks over the M6 motorway itself.

“This achievement is a testament to our collective effort and a fantastic milestone for the immediate team and the whole project.”

Don't miss anything, follow us on social media !