Technical details
Client
TCDD
Dates

2013 – 2018

Missions
Preliminary Design, Detailed Design
Location
Uşak – Manisa, Türkiye
Activity
High Speed Railways

This 74 km segment forms part of the Ankara–İzmir HSR, traversing difficult seismic terrains. The line supports 250 km/h, with 21 viaducts, 24 tunnels, and 47 road connections. SYSTRA carried out preliminary and detailed design services for TCDD from 2013 to 2018

Key Figures

  • 74 km long HSR
  • 250 km/h design speed
  • 21 viaducts
  • 24 tunnels
  • 8 adit tunnels
  • 9 cut&covers
  • 39 underpasses
  • 12 overpasses
  • 47 culverts
  • 47 road connections