Technical details
Client
TCDD
Dates

2012-2018

Missions
Preliminary Design, Detailed Design
Location
Adana – Osmaniye, Türkiye
Activity
Railway

The project purpose is to connect Toprakkale Station to Bahçe Station by doubling the existing line in some sections. The line consists of 5 tunnels and 5 viaducts. There is also a station in Düziçi. 

Key Figures

  • 160km/h design speed
  • 5 viaducts
  • 5 tunnels (double tube)
  • 8 adit tunnels
  • 3 cut&covers
  • 21 underpasses
  • 15 overpasses
  • 88 culverts
  • 37 road connections
  • 1 stations