title: "Dalfaber&#8217;s Safer Level Crossing for New Housing Development "
url: "https://www.systra.com/uk/project/dalfaber-level-crossing/"
type: projects
date_published: 2023-03-07
date_modified: 2026-04-30
schema:
  @type: WebPage
language: en-GB
word_count: 1259
reading_time: 7 min
canonical: "https://www.systra.com/uk/project/dalfaber-level-crossing/"
featured_image: "https://www.systra.com/uk/wp-content/uploads/sites/11/2023/03/test-locomotive-at-dalfaber-lc-2380-1500px-crop.jpg"
type-market:
  - Sustainable Transport
project-market:
  - "Highways &amp; Roads"
  - Rail
project-location:
  - "Highlands &amp; Islands"
  - Scotland
---

# Dalfaber’s Safer Level Crossing for New Housing Development 

![Dalfaber’s Safer Level Crossing for New Housing Development ](https://www.systra.com/uk/wp-content/uploads/sites/11/2023/03/test-locomotive-at-dalfaber-lc-2380-1500px-crop.jpg)

### Housing development needs new level crossing to provide safe access

**Residential property developer, Scotia Homes, had been granted planning permission to build a housing estate in Aviemore, Scotland. The permission included a condition that a level crossing on the access road to the site had to be upgraded, to safely accommodate increased traffic levels. Scotia Homes was not permitted to sell homes on the site until the upgraded level crossing was operational. **

The existing Dalfaber Level Crossing was an Automatic Open Crossing, with no
barriers to separate road traffic from trains and only flashing lights and bells
to warn of an approaching train. There had been a number of near misses and
collisions at the crossing over the years.

The track infrastructure at the crossing was owned by heritage operator,
Strathspey Railway, while the level crossing itself and its ongoing maintenance
were the responsibility of The Highland Council. Scotia Homes needed to deliver
a safer level crossing for Strathspey Railway, while ensuring it was suitable
for The Highland Council to operate and maintain over the long term.

With no in-house expertise in level crossing design and development, Scotia
Homes appointed SYSTRA to consult with all stakeholders and deliver an
appropriate solution.

![dalfaber-level-crossing-construction-2](https://www.systra.com/uk/wp-content/uploads/sites/11/2023/03/dalfaber-level-crossing-construction-2.jpg)

### Optimum level crossing solution meets all stakeholder needs

To help Scotia Homes manage cashflow, SYSTRA provided a detailed cost schedule
for the project. Costs were distributed throughout the programme, so that funds
would be available at the right time to keep the project on schedule.

SYSTRA played a pivotal role in liaising with stakeholders Scotia Homes,
Strathspey Railway, The Highland Council and – latterly – Principal Contractor
WM Donald, as well as the Office of Rail and Road (ORR), which would ultimately
sign off the new Level Crossing Order.

Based on the expected rail, road and pedestrian usage, the funding arrangements
and the available maintenance skills, SYSTRA proposed an Automatic Barrier
Crossing (Locally Monitored) as the optimum solution. This type of crossing
features half barriers across the road, which lower automatically when a train
approaches. Train drivers must ensure the barriers have operated correctly and
the crossing is clear before proceeding.

![Dalfaber-1-1000-old-level-crossing](https://www.systra.com/uk/wp-content/uploads/sites/11/2023/03/dalfaber-1-1000-old-level-crossing.jpg)

_Old Level Crossing_

![Dalfaber-2-1000-new-level-crossing](https://www.systra.com/uk/wp-content/uploads/sites/11/2023/03/dalfaber-2-1000-new-level-crossing.jpg)

_Upgraded Level Crossing_

Crucially, this design addressed the needs of all stakeholders. As a heritage
railway operator, Strathspey Railway lacked the resources or technical skills
usually available on the main railway network, while the local council had no
specialist in-house expertise in railway level crossing maintenance.

### Multi-disciplinary project team keeps programme on track

The SYSTRA Level Crossings team implemented a three-stage strategy to minimise
financial exposure for Scotia Homes while enabling the project to progress on
schedule.

- **Stage 1** – an initial Suitable and Sufficient Risk Assessment was produced
  to define the proposed level crossing type.
- **Stage 2 **– an Approval in Principle Level Crossing Ground Plan was
  produced, and used to begin formal consultation with the ORR and The Highland
  Council. This was developed through to an Approved for Construction Ground
  Plan.
- **Stage 3** – Detailed Design was undertaken by all disciplines to make the
  upgraded level crossing a reality.

Supporting disciplines on the project were able to move straight to Detailed
Design, once the level crossing type and layout had been agreed. This innovative
approach helped to minimise cost, effort and time for the initial stages of the
project, allowing the design team to focus immediately on the final proposals.

![dalfaber-level-crossing-plan-1000](https://www.systra.com/uk/wp-content/uploads/sites/11/2023/03/dalfaber-level-crossing-plan-1000.jpg)

![dalafabar-head-2](https://www.systra.com/uk/wp-content/uploads/sites/11/2023/03/dalafabar-head-2-1024x645.jpg)

![dalfaber-lc-zn-corner](https://www.systra.com/uk/wp-content/uploads/sites/11/2023/03/dalfaber-lc-zn-corner.jpg)

The signalling design was sub-contracted to Strathspey Railway, with SYSTRA
providing the physical CAD drawings. SYSTRA also produced the Draft Level
Crossing Order for the project.

SYSTRA
[civil engineers](https://www.systra.com/uk/services/infrastructure-engineering/civil-engineering/)
produced foundation designs for the crossing, while our
[E&P team ](https://www.systra.com/uk/services/technical-systems/mechanical-electrical-engineering/)
delivered electrical designs to power the new crossing and the Relocatable
Equipment Building (REB) for the signalling circuits. We also carried out a
track condition survey and provided an appropriate track design and risk
assessments for the level crossing proposals. Our
[highways specialists ](https://www.systra.com/uk/services/development-infrastructure/highways-and-drainage/)
designed a road alignment to mitigate the risk of long, low vehicles grounding
at the crossing.

A topographical survey of the existing level crossing was carried out by our
[Site Services team](https://www.systra.com/uk/services/engineering-management/site-services/)
, and used by all disciplines on the project. The team also performed
ground-penetrating RADAR scans of the area and dug observation pits to locate
buried utilities. Despite this meticulous preparation, an undetected sewage pipe
was found during excavations for the new road traffic lights. SYSTRA quickly
stepped in to revise the foundation designs to accommodate the pipe, without
altering the position of the traffic lights.

SYSTRA actively managed the entire design stage of the project and acted as
Principal Designer, ensuring the client was aware of all its responsibilities
under the CDM Regulations. This included supplying pre-construction information
and collating the Health and Safety File after commissioning.

### Safe, modern level crossing commissioned on schedule

On the agreed date, the SYSTRA-designed Dalfaber level crossing was successfully
commissioned and signed into use on the public highway. This was the culmination
of two and a half years of coordinated hard work and effort. The new crossing
included LED road traffic lights and an improved footway and lighting for the
public.

The successful project gave Scotia Homes the level crossing safety it needed to
complete its new housing development. Strathspey Railway benefited from a safe,
modern crossing, while the Highland Council gained a significantly improved
asset that provided a far safer crossing for pedestrians and road users.
Strathspey Railway reported that in the year after the new level crossing was
introduced, there was not a single vehicle or pedestrian-related incident at the
crossing.

[level crossings & technical systems ](https://www.systra.com/uk/services/technical-systems/level-crossings/)

[JOIN OUR COMMUNITY](https://www.systra.com/uk/register/join-our-community/)

Some examples of projects in Highways & Roads, Rail

[  Pioneering Local Development Order unlocks sustainable growth at Milton Park in Oxford ](https://www.systra.com/uk/project/pioneering-local-development-order-unlocks-sustainable-growth-at-milton-park-in-oxford/)
[  Transport for the North: Spatial Data Visualisation Platform  ](https://www.systra.com/uk/project/transport-for-the-north-data-visualisation-platform/)
[  IAMP: Building an advanced manufacturing park for Sunderland and South Tyneside ](https://www.systra.com/uk/project/iamp-building-an-advanced-manufacturing-park-for-sunderland-and-south-tyneside/)
[  Increasing capacity, safety and sustainability at Key Street junction in Kent  ](https://www.systra.com/uk/project/increasing-capacity-safety-and-sustainability-at-key-street-junction-in-kent/)
[  Transport Decarbonisation Strategy for Dalton Industrial Estate ](https://www.systra.com/uk/project/transport-decarbonisation-strategy-for-dalton-industrial-estate/)
[  Kent County Council: Grovehurst A249 Junction Improvement ](https://www.systra.com/uk/project/kent-county-council-grovehurst-a249-junction-improvement/)

[ See a selection of SYSTRA's projects ](https://www.systra.com/uk/project/kent-county-council-grovehurst-a249-junction-improvement/)