project-market:
  - Transit Bridges
  - Segmental Bridges
project-location:
  - Saudi Arabia
---

# Riyadh Metro, Line 3 – Riyadh, Saudi Arabia

![Riyadh Metro, Line 3 – Riyadh, Saudi Arabia](https://www.systra.com/ibt/wp-content/uploads/sites/21/2020/01/dsc_1076-scaled.jpg)

## DESIGN-BUILD

**Total Length: **180 km (111.8 mi)
**Elevated Viaduct:** 26.4 km(16.4 mi)

**The Riyadh Metro is a rapid transit system under construction in Riyadh, Saudi Arabia, which includes 6 different lines with a total length of about 180 km (111.8 mi). Riyadh Metro Line 3, the longest elevated line, runs in the East-West direction along Al Madinah Al Munawwarah and Prince Saad Bin Abdulrahman Al Awal Roads, starting at the west near Jeddah Expressway and ending at the east near the National Guard Camp of Khashm El Aan.**

The Metro is mostly elevated along the western part of Al Madinah Al Munawwarah
Road, then underground in bored and mined tunnels in the central section of the
line, and elevated again along Salah Al Din Al Ayoubi Road. The length of Riyadh
Metro Line 3 is approximately 41.6 km (25.3 mi), and it features 20 stations.

The 26.4 km (16.4 mi) elevated viaduct consists of a three-cell precast
segmental box girder with typical spans of 37 m (122 ft) and special continuous
spans of 50 m (164 ft). Six long span structures with spans varying from 60 m to
95 m (197 ft to 312 ft) are required for the special crossings over existing
interchanges. Typical and continuous spans are erected span-by-span with an
overhead truss. Long spans are erected in a balanced cantilever with cranes on
the ground or lifting frames on the deck.

SYSTRA IBT was responsible for the design of the viaduct from the conceptual
tender stage through the 100% detailed design stage. Along with the detailed
design, SYSTRA IBT was in charge of the construction engineering and complete
shop drawing production of the line, with site-based support staff assisting the
contractor.

## Featured Projects

Some examples of projects in Segmental Bridges, Transit Bridges

[  Surrey Langley SkyTrain – Langley, BC, Canada ](https://www.systra.com/ibt/project/surrey-langley-skytrain-langley-b-c-canada/)
[  Hart Metro, Contract 3 – Honolulu, Hawaii ](https://www.systra.com/ibt/project/hart-metro-contract-3-honolulu-hawaii/)
[  Mosquito Road Bridge – El Dorado County, California ](https://www.systra.com/ibt/project/mosquito-road-bridge-el-dorado-county-california/)
[  Reseau Express Metropolitain (REM) – Greater Montréal, Canada ](https://www.systra.com/ibt/project/reseau-express-metropolitain-rem-greater-montreal-canada/)
[  Davenport Diamond Guideway Project – Toronto, Ontario, Canada ](https://www.systra.com/ibt/project/davenport-diamond-guideway-project-toronto-ontario-canada/)
[  Chicago Transit Authority (CTA) Red-Purple Modernization Project – Chicago, Illinois ](https://www.systra.com/ibt/project/chicago-transit-authority-cta-red-purple-modernization-project-chicago-illinois/)

[ See a selection of SYSTRA's projects ](https://www.systra.com/ibt/project/chicago-transit-authority-cta-red-purple-modernization-project-chicago-illinois/)