title: Securing of the Arles-Tarascon railway line – France
url: "https://www.systra.com/en/projects/securing-of-the-arles-tarascon-railway-line-france/"
type: projects
date_published: 2024-06-07
date_modified: 2024-06-07
schema:
  @type: WebPage
language: en-US
word_count: 341
reading_time: 2 min
canonical: "https://www.systra.com/en/projects/securing-of-the-arles-tarascon-railway-line-france/"
featured_image: "https://www.systra.com/wp-content/uploads/2024/06/arles-tarascon-scaled.jpeg"
type-market:
  - Rail
project-market:
  - Rail
  - Conventional Rail
project-service:
  - Design
  - Project Management and Construction
project-location:
  - France
---

# Securing of the Arles-Tarascon railway line – France

![Securing of the Arles-Tarascon railway line – France](https://www.systra.com/wp-content/uploads/2024/06/arles-tarascon-scaled.jpeg)

**In 2021, the hydraulic transparency of the railway line linking the cities of Arles and Tarascon in the Bouches-du-Rhône department of France was completed with the installation of the last two railway bridges. A long-term assignment led by SYSTRA since 2011.**

The last operation involved 150 workers for 42 hours. During this operation, the
framework bridges were installed using an original method, usually used to
install gantries: the Kamag\* method. The line was handed back to SNCF Reseau 5
hours ahead of schedule.

This project, linked to the Rhône Plan\*\*, is a first in France. After several
years of studies, the installation of the 10 railway bridges began in 2019,
necessitating prolonged closures of the line during major operations.

**MONUMENTAL STRUCTURES**

The size of each bridge is impressive. On average 4 metres high, 28 metres long,
22 metres and a mass of 1,700 tonnes of iron and concrete. This is what was
needed to provide optimum support for the double-track railway. Their
installation required a 192-wheel hydraulic jack.

\*The Kamag method owes its name to a self-propelled transporter. It is a
platform vehicle with numerous axles enabling very heavy quantities to be
shifted in special convoys over short distances.

\*\* A plan to protect the region from flooding following the 2003 flood which
affected more than 12,000 people and caused 700 million euros of damage.

Some examples of projects in Rail, Conventional Rail, Design, Project Management
and Construction

[  Villemur-sur-Tarn School Complex – France  ](https://www.systra.com/en/projects/villemur-sur-tarn-school-complex-france/)
[  Taranto station multimodal interchange -Italy ](https://www.systra.com/en/projects/taranto-station-multimodal-interchange-italy/)
[  SBIOA Unity Enclave – Chennai, India ](https://www.systra.com/en/projects/sbioa-unity-enclave-chennai-india/)
[  Orly Airport Station – France ](https://www.systra.com/en/projects/orly-airport-station-france/)
[  Arena Amazonia, Manaus – Brazil ](https://www.systra.com/en/projects/arena-amazonia-manaus-brazil/)
[  Line 15 South Stations (Grand Paris Express) – France ](https://www.systra.com/en/projects/line-15-south-stations-grand-paris-express-france/)

[ See a selection of SYSTRA's projects ](https://www.systra.com/en/our-projects/)