title: Two metro lines extended in the Paris region thanks to SYSTRA
url: "https://www.systra.com/en/news/two-metro-lines-extended-in-the-paris-region-thanks-to-systra/"
type: post
date_published: 2024-07-01
date_modified: 2024-09-12
schema:
  @type: Article
language: en-US
word_count: 1071
reading_time: 6 min
canonical: "https://www.systra.com/en/news/two-metro-lines-extended-in-the-paris-region-thanks-to-systra/"
featured_image: "https://www.systra.com/wp-content/uploads/2024/07/vignette.png"
categories:
  - Non classé
---

# Two metro lines extended in the Paris region thanks to SYSTRA

![Two metro lines extended in the Paris region thanks to SYSTRA](https://www.systra.com/wp-content/uploads/2024/07/vignette.png)

### Extension of line 14, backbone of the Grand Paris Express

From 24 June 2024, line 14 of the Paris metro extends as far north as
Saint-Denis-Pleyel and as far south as Orly Airport. This makes it the longest
line on the Paris [metro](https://www.systra.com/en/markets/metro/) and the
backbone of the Grand Paris Express.

The inauguration took place in the presence of the President of France Emmanuel
Macron, the President of The Regional Council of Île-de-France Valérie Pécresse,
the CEO of RATP Jean Castex, the Chairman of the Board of SGP Jean-François
Monteils, and the CEO of the ADP Group Augustin de Romanet.

SYSTRA’s representatives on the day included Pierre Verzat, CEO, Nathalie
Retout, Director of Urban Projects, Île-de-France, Jean-Yves Reynaud, Director
of Production, France and International, and François Lhomond, Project Director.

### Nearly a decade of projects for SYSTRA on line 14 south

Since June 2015, SYSTRA has been working alongside Setec TPI (leader of the
Elios consortium) as project manager for all the infrastructure, along with five
architectural practices\*. From civil engineering to development, SYSTRA has
been involved at every stage of the construction of
[the tunnel](https://www.systra.com/en/markets/tunnels-underground-structures/)
and stations, particularly for Maison Blanche station, the only Parisian station
on the section to be built in an ultra-dense urban environment. We were also
responsible for overseeing the structural work on the Orly terminus station,
under a project management contract signed with ADP.

From studies of the route and structures to monitoring their construction,
SYSTRA France’s teams worked day in, day out to meet the deadlines for a project
whose entry into service was brought forward to coincide with the summer sports
events. We were also responsible for low-voltage systems, ventilation, and smoke
extraction throughout the tunnel, as well as environmental, acoustic and
vibration studies of the route.

![](https://www.systra.com/wp-content/uploads/2024/07/vincent-duguay-2-1-683x1024.jpg)

> It was a great source of pride to be present at the inauguration of this
> extension, a flagship project for the Urban Projects Department and an
> undisputed benchmark for our technical expertise. We are also proud that
> SYSTRA is the only engineering company to have been involved in all the
> projects for line 14 since its creation in the 1990s, and then for its
> extension to Mairie-de-Saint-Ouen until 2021, and now 2024. Finally, I am
> proud that, with our partners, we will be taking part in the sporting events
> to come this summer. Congratulations to the teams who have been involved at
> every stage of this emblematic project.
> Vincent Duguay, Director of the Urban Projects Department (DPU), SYSTRA France

### Renewal of the automation system: a world first

Another highlight of this extension is the renewal of the train operation
automation system (SAET), to which SYSTRA France contributed from design to
commissioning. Line 14 will go down in history as the first line to have its
automatic train control system replaced, without any interruption to service or
impact on commercial operations.

The teams were also involved in the Systems Project Management for the
signalling equipment at the Morangis maintenance and storage site, located
beyond Orly, which houses half of the 75 trainsets planned for operation.

### The Grand Paris Express is taking shape

With the extension of line 14, the Grand Paris Express is becoming a reality for
the people of the Paris region. With 7 new stations serving 5 new communes, the
line will soon be used daily by 800,000 passengers, making it the busiest metro
line in France.

An eighth station, Villejuif – Gustave Roussy, will open by the end of 2024: it
will be one of the two transfer stations between line 14 and line 15, the first
section of which to the south is expected to open in 2025. This should make the
Grand Paris project a reality, offering new mobility solutions to all residents
of the Paris region.

![pcc-photo-credit-ratp_sylvain_cambon](https://www.systra.com/wp-content/uploads/2024/06/pcc-photo-credit-ratp_sylvain_cambon-scaled.jpg)

_The Operation Control Centre of line 14, installed at Bercy_

### To the east of Paris, the extension of line 11 brings Seine-Saint-Denis closer to the capital

On June 13, the extension of line 11 of the Paris metro was brought into
service. The inauguration took place in the presence of the President of the
Paris region, Valérie Pécresse, of the Minister of Transport Patrice Vergriete,
and Jean-Yves Reynaud, Director of Production France and International at the
DPU and Nathalie Retout for SYSTRA.

Line 11 now links Les Lilas to Rosny-sous-Bois and provides direct access to the
centre of Paris and the Châtelet-Les Halles hub. For SYSTRA, this is the
culmination of 10 years’ work, which began in 2014 as leader of the project
management consortium, in association with Artelia and Richez\_Associés.

![img_9208](https://www.systra.com/wp-content/uploads/2024/06/img_9208-scaled.jpg)

_The Maintenance and Storage Site at Morangis_

### SYSTRA involved at every stage

SYSTRA was involved in all phases of the project, which includes 4 stations, a
tunnel excavated with a tunnel boring machine and ventilation and fire-fighting
access structures, as project manager for the extension’s infrastructure and
fittings, from design and execution through to acceptance of the underground
section.

With this extension, which will link up with the RER E (Rosny-Bois-Perrier) and
the T1 tramway (Romainville-Carnot), line 11 will expand mobility services
within the region, and open up new prospects thanks to a future connection with
line 15 East scheduled for 2031, and eventually a second extension to
Noisy-Champs.

> The whole SYSTRA team is very proud to see this project come to fruition, and
> to be on schedule for the summer of 2024. This extension has been long-awaited
> by local residents, who will now be able to benefit from a direct metro line
> to the heart of the capital in less than half an hour and relieve congestion
> on existing services. Well done to the various teams and support services who
> have worked for all these years to make this project a success! I would also
> like to mention the partnership with our co-contractors, which has been
> constructive at every stage of the project.
> Nathalie Retout, Director of Metros, Île-de-France, DPU, SYSTRA France