title: "Inauguration of the Waaban Bridge in Kingston, Canada"
url: "https://www.systra.com/en/news/inauguration-of-the-waaban-bridge-in-kingston-canada/"
type: post
date_published: 2022-12-20
date_modified: 2022-12-20
schema:
  @type: Article
language: en-US
word_count: 773
reading_time: 4 min
canonical: "https://www.systra.com/en/news/inauguration-of-the-waaban-bridge-in-kingston-canada/"
featured_image: "https://www.systra.com/wp-content/uploads/2022/12/thirdcrossing-johnandrew-sept9_22.jpg"
categories:
  - Non classé
---

# Inauguration of the Waaban Bridge in Kingston, Canada

![Inauguration of the Waaban Bridge in Kingston, Canada](https://www.systra.com/wp-content/uploads/2022/12/thirdcrossing-johnandrew-sept9_22.jpg)

The Kingston Third Crossing project is over: the Waaban Crossing Bridge is here!
This new Ojibwe language name\*, which evokes the dawn and the morning light in
the east, was chosen after a survey of local residents. Inhabitants had to
opportunity to cross this structure on foot in the preview event on 24 September
2022. As of today the bridge is now open, for both vehicles and soft modes,
which benefit from separate lanes. The Waaban Bridge connects the east and west
sides of Kingston, separated by the Cataraqui River, which flows nearby into
Lake Ontario and forms part of the Rideau Canal, a UNESCO World Heritage Site.

This third bridge over the Cataraqui River is intended to relieve traffic
congestion and facilitate the movement of emergency vehicles from one side of
the river to the other, while also contributing to the development of active
transportation.

\*Ojibwe: Algonquian language spoken in the Great Lakes region. It is one of the
most widely spoken Amerindian languages.

![default](https://www.systra.com/wp-content/uploads/2022/12/kingston-third-crossing_on-20-1604514454-2-scaled.jpg)

_During the construction_

This third bridge over the Cataraqui River is intended to relieve traffic
congestion and facilitate the movement of emergency vehicles from one side of
the river to the other, while also contributing to the development of active
transportation.

![zac-1](https://www.systra.com/wp-content/uploads/2022/12/zac-1.jpg)

> We are proud to have been involved in the design and construction of this
> major bridge for the people of Kingston and the Lake Ontario region. Over the
> past five years, we have worked with our partners the City of Kingston, Kiewit
> and Hatch to ensure that this bridge meets the ambitions of our client and the
> community.
> Zac McGain, project director, SYSTRA IBT

> This bridge will make a difference to the lives of residents and will bring
> Kingston’s two shores closer together. I would like to thank all the teams who
> have been involved in making this project, the first to be carried out
> entirely by SYSTRA IBT, a great success!
> Edouard Renneville, project manager, SYSTRA IBT

![renneville-1](https://www.systra.com/wp-content/uploads/2022/12/renneville-1.jpeg)

### A new form of contract for a pioneering project

This inauguration is the culmination of a construction project that began five
years ago and was launched in 2017, just a few months after International
Bridges Technologies became part of the SYSTRA Group. One of the particularities
of the project is its contractual form: SYSTRA IBT, the engineering firm Hatch
and the construction company Kiewit formed an IPD (Integrated Project Delivery)
contract with the City of Kingston, an integrated grouping that is a first in
North America for linear infrastructure. One challenge is that it is the largest
transportation project ever funded in Kingston’s history.

### A bridge for the environment

The benefits of this project are also environmental: in addition to the modal
shift and the decongestion of road traffic, it has an overall footprint in water
that is more than 50% smaller than the initial environmental assessment. Its
visual impact on the Rideau Canal UNESCO site has also been reduced, thanks to
close dialogue with local stakeholders and the heritage community. The IPD
consortium implemented solutions to ensure the navigability of the Rideau Canal
between spring and autumn without delaying the work, such as a mixed
construction, with a temporary trestle bridge on one side and temporary rock
fill on the other to allow for the foundations.

I-beams, known as ‘NU’ in reference to the University of Nebraska, which
designed them, were used in the construction. They are prefabricated in
pre-stressed concrete and offer greater resistance to flexion-torsion. Finally,
it should be noted that the structure delivered to the Kingston authorities
exceeds the legal requirements for the design of such a bridge: planned to last
75 years, the Waaban Bridge was designed for a final life of 100 years. This is
a great achievement for a project that the authorities welcome as being
delivered on time and on budget.

![default](https://www.systra.com/wp-content/uploads/2022/12/kingston_kingston_internal_06-1604514302-2-scaled.jpg)

### Key facts – Kingston Waaban Bridge

- 2 lanes of road traffic and 1 bi-directional lane dedicated to soft modes, 4
  metres wide
- Bridge length: 1.2km, with 800 metres of approach lanes
- Deck width: 15.6m
- Designed to last 100 years
- 95 pre-stressed concrete I-beams, known as NU beams, for the approach
  crossings

- 1,695 pre-stressed concrete plates to form the deck
- 3,300 tonnes of steel for the main span structure’s framework
- 31,000 tonnes of concrete
- 365,000 tonnes of gravel for the foundations
- Over 29,000 hours of work by local workers