SYSTRA won the contract to project manage the southward extension of Line 4 of the Paris metro beyond the former terminus at Porte d’Orléans, to Montrouge and Bagneux.

The work was carried out in two phases using conventional construction methods. Phase 1 involved the construction of a station at Mairie de Montrouge; and Phase 2 the construction of two stations “Verdun Sud” and “Bagneux” in a dense urban area.

The full line extension is due for commissioning in 2020 by which time, Line 4 will also have been fully automated and the terminus at Bagneux will connect to Line 15 of the Grand Paris Express.

SYSTRA’s Role

SYSTRA was responsible for full project management from the design phase through to the supervision of civil engineering works (carcass and finishing work) as well as for non-systems related installations (fluids, low voltage power, MEP) during each of the following phases:

  • Preliminary design
  • Detailed design
  • Works contract assistance
  • Planning study certificates
  • Works contract delivery
  • Acceptance operation assistance.

SYSTRA was also in charge of the following for the entire project:

  • Coordination technical activities
  • Summarising designs during the construction phase
  • Production of signalling diagrams
  • Conducting and following up on geotechnical surveys.
Top of the page

Read also

Grand Paris metro – Line 15 south
Grand Paris metro – Line 15 south
The new Grand Paris metro network will provide outlying districts with (...)
Paris Region - New Tram-Train T4 branch
Paris Region - New Tram-Train T4 branch
A new branch will be added to the T4 Line, the first tram-train to be (...)
Urban cable car of Orléans – France
Urban cable car of Orléans – France
SYSTRA, as part of the VINCI consortium, realizes design studies and (...)
Modernisation of Corsica’s railway
Modernisation of Corsica’s railway
The Corsican Authorities (CTC) renewed their confidence in SYSTRA, awarding (...)
Motorway – Diversions for the SEA HSL
Motorway – Diversions for the SEA HSL
As the main design consultant on the SEA (South-East Atlantic) HSL between (...)
France – Reopening of the Echoppes Triangle
France – Reopening of the Echoppes Triangle
With the reopening of the Triangle des Echoppes junction, passengers from (...)
France – Val’Tram – Aubagne LRT
France – Val’Tram – Aubagne LRT
SYSTRA won the project management contract to build the new Val’Tram LRT (...)
Nîmes-Montpellier HSR Rail By-Pass
Nîmes-Montpellier HSR Rail By-Pass
The Nimes-Montpellier rail by-pass is a ground-breaking project. It’s the (...)
France – Upgrade of the Niort – La Rochelle Rail Line
France – Upgrade of the Niort – La Rochelle Rail Line
SYSTRA is in charge of integrated project management activities on the (...)
France – T1 LRT Extension from Asnières to Colombes
France – T1 LRT Extension from Asnières to Colombes
SYSTRA won the contract to manage the T1 LRT/tramline extension from (...)
Motorway – A4 Diversion – Eastern Europe HSR
Motorway – A4 Diversion – Eastern Europe HSR
SYSTRA won the project management contract to design and build the East (...)
Motorways – Widening of the A13
Motorways – Widening of the A13
SAPN (the operator of the Paris-Normandy Motorway) awarded SYSTRA, the lead (...)
SYSTRA 72, rue Henry Farman 75015 Paris - France - T. +33 1 40 16 61 00
Contact